Module 3 · Schedule Development · Week 2 · Interactive Companion
The same twenty Heron Pond Connector Path tasks you structured in the WBS Builder are now sequenced in time. Place every task into its schedule window, working backward from the advertisement date. Protect the reviews the firm does not control. Then lock your schedule and present it two ways.
Used live in the Week 2 session · steps 1 through 5 of the Schedule Development ProcessWork left to right. Click a task in the bank, then click the schedule window where it belongs, or drag it there. At every chip, ask the Week 1 question, which tasks shall be complete before this task can begin. Place the three buffer chips onto the amber targets between windows, in front of the review each buffer protects.
Your locked schedule, presented two ways
This view presents two perspectives on the same schedule, the two views Week 1 named. The Milestone Schedule is what the Town tracks. The Schedule of Activities is what your team works from. Toggle between them. This is your build, not a single forced correct answer. Use the Check function or the model reveal to compare your build against the model sequence.