Module 1 · Week 4 · Interactive Lesson

Build the Proposal Schedule

PROJECT MANAGEMENT 101 AT WESTON & SAMPSON

MODULE 1 · WEEK 4

Build the Proposal Schedule

THE PROBLEM

The Millbrook response is due Tuesday 29 September at 2:00 P.M. The solicitation gave 21 days. The kickoff meeting was held Wednesday 16 September.

How many working days does the technical team have to write?

What is given

Solicitation advertised
Tuesday 8 September 2026
Pre-proposal conference
Tuesday 15 September 2026
Proposal kickoff meeting
Wednesday 16 September 2026
Written questions close
Friday 18 September 2026
Marketing starts production
Friday 25 September 2026
Proposal due
Tuesday 29 September 2026, 2:00 P.M.
The Technical Lead is out
Tuesday 22 September 2026
Working days
Monday through Friday. No holiday falls in this window.

Answer Steps 1 and 2 with the day of the month in September. Answer Step 3 with a whole number of working days.

Step 1Fixing the end, working backward from the deadline

Written Lesson, Section 1.4.5

Build the proposal schedule backward from the due date. Two rules set the end of technical writing, and both come from our firm rather than the solicitation.

Millbrook RFP 26-014 · Solicitation 26-014, cover sheet
Solicitation26-014, CRA Infrastructure Improvements, Cypress Landing East (CLE) Public Utilities Renewal (TownPUR) Project, RFP (CCNA)
Notification date08 September 2026
Pre-proposal conference15 September 2026, 10:00 A.M.
Written questions close18 September 2026, 5:00 P.M.
Opening date and time29 September 2026, 2:00 P.M.

A non-mandatory pre-proposal conference will be held September 15, 2026 at 10:00 A.M. local time.

Weston & Sampson · the two standing rules

Package an electronic submission 24 hours before the deadline. The deadline is Tuesday 29 September, so packaging happens Monday 28 September.

All technical components are complete 24 hours before Marketing starts production. Marketing starts production Friday 25 September.

Weston & Sampson · the September 2026 calendar
MonTueWedThuFri
1415 conference16 kickoff1718 questions close
2122 Technical Lead out232425 production starts
28 package29 due 2:00 P.M.

On which September date must the technical components be complete?

SeptemberSeptember

Two tries. After the second the page shows the worked solution and carries the correct value forward.

Worked solution

Marketing starts production Friday 25 September. Technical components are complete 24 hours before that.

Thursday 24 September

Packaging on Monday 28 September is Marketing's deadline, not the technical team's.

Step 2Fixing the start, working forward from the kickoff

Written Lesson, Sections 1.4.2.1 and 1.4.5

Writing cannot begin before the team is known. Marketing sets that date at the kickoff meeting.

Weston & Sampson · what Marketing needs, and when

The Go/No-Go form complete in Deltek Vantagepoint two weeks before the deadline, with the Technical Lead's commitment line signed. That was Tuesday 15 September.

The team confirmed within 48 hours of the kickoff meeting. The kickoff was Wednesday 16 September, so the team was confirmed Friday 18 September.

Subconsultants introduced to Marketing within 24 hours of the kickoff.

Technical writing starts the first working day after the team is confirmed.

Technical components complete, from Step 1This fills in when the step above is checked.

On which September date does technical writing start?

SeptemberSeptember

Two tries. After the second the page shows the worked solution and carries the correct value forward.

Worked solution

The team is confirmed Friday 18 September. The first working day after that is Monday 21 September.

Monday 21 September

Friday 18 September is the confirmation day, not a writing day.

Step 3Counting the working days

Written Lesson, Section 1.4.5, and the TIP on building backward

Build the schedule around the holidays and the vacations of the people the team depends on. A day the Technical Lead is out is not a writing day for the technical team.

Weston & Sampson · the September 2026 calendar, again
MonTueWedThuFri
21 writing starts22 Technical Lead out2324 technical complete25 production starts
Writing starts, from Step 2This fills in when the step above is checked.
Technical components complete, from Step 1This fills in when the step above is checked.

How many working days does the technical team have to write?

working days

Two tries. After the second the page shows the worked solution and carries the correct value forward.

Worked solution

Monday 21 September through Thursday 24 September is four working days. The Technical Lead is out on Tuesday 22 September.

4 − 1 = 3 working days

A 21 day window produced three days of technical writing. The rest of the window went to the Go decision, the conference, the kickoff, team confirmation, production and packaging.

The writing window

Complete bynot yet
Writing startsnot yet
Working daysnot yet

Three working days. One of them would disappear entirely if the kickoff slipped by 48 hours, and two would disappear if Marketing needed production a day early.

Nothing here was a surprise. Every date came from the solicitation or from a standing rule our firm already had.

The takeaway

Build the schedule backward from the due date, around the holidays and vacations of the people the team depends on.

A 21 day window is not 21 days of writing. Fix the end first, fix the start second, then count what is actually left.