Module 3 · Schedule Development · Week 1 · Interactive Studio
Five steps turn a scoped work breakdown into a Schedule of Activities you can defend. Complete each step on the real Heron Pond Connector Path network. Place the work, test the logic, and observe whether the plan holds or breaks.
Five staged steps · about 15 minutes · builds on the Critical Path SpotterReview the Work Breakdown Structure
Goal. Confirm that every schedule activity traces back to scoped work. Do not add anything to the schedule that was not already in the plan.
A schedule does not introduce new work. It sequences the same work already broken down in the Work Breakdown Structure, now placed in time. Module 2 locked the Heron Pond work breakdown structure. Below are the four deliverables and the work packages under them.
Ten of these tasks form the 75 to 100 percent schedule. Open each activity below to trace it back to its work package. When you have opened all ten, you have identified the complete set of schedulable work.
Identify dependencies
Goal. For each activity, name the work that has to finish first. This dependency logic is what distinguishes a schedule from an unfounded guess.
Ask the same question for every task. What has to be finished before this task can begin. Task A starts at notice to proceed and has no predecessor. For the remaining tasks, select the predecessors from the choices shown. Some choices are incorrect and are included to test your understanding of the dependency logic.
Build the critical path
Goal. Mark the activities on the longest path through the network. That chain determines the promised completion date. Every other activity carries slack.
Now that the logic is set, add the durations along every route from start to finish. The longest route is the critical path. A slip on any activity on that path delays the finish date for the whole project. Select the activities you believe sit on that path, then check your selection.
Assign float
Goal. Quantify the slack for each activity. Float is the number of weeks an activity can be delayed before it delays the finish date.
An activity on the critical path has zero float. An activity that is not on the critical path can start late or run long without cost, until its float is used. For each activity below, set its float in weeks. Two of these activities sit on the critical path. Two do not.
Review forward
Goal. Read the finished Schedule of Activities, then apply the pressure test questions below. A plan you have not tested is a plan you cannot yet trust.
Below is the network you built, sorted into a Schedule of Activities. Red bars indicate activities on the critical path. Teal bars indicate activities that carry float, shown with a hatched tail for the amount of float they carry. The amber line marks the week the Owner review opens.
Now apply the pressure test. Answer each question, then reveal what the network actually does.
You did not guess a duration. You started from defined work, set the dependency logic, identified the chain that determines the finish date, measured the float in every other activity, and tested the complete schedule by walking it forward.