Project Management 101
This course site is shared for review. Enter the access code to continue.
That code didn't match. Try again.
Weston & Sampson · AEC LEAD
Course
produced by
Created by
AEC LEAD LLC
Module 1 · Week 1 · Interactive Lesson

What a Pursuit Costs

PROJECT MANAGEMENT 101 AT WESTON & SAMPSON

MODULE 1 · WEEK 1

What a Pursuit Costs

THE PROBLEM

The Town of Millbrook issues RFP 26-014. Our firm decides to pursue it. Three technical staff spend time on the proposal, and all three had billable work available in the same two weeks.

Suppose this was a pursuit our firm should have declined. What did it cost?

What is given

Technical salary
$72,800 a year, the figure Module 0 works
Working hours in a year
2,080
Overhead rate
1.85
Target ELM
3.30
Billable work available
Yes, for all three technical staff, in the same two weeks

Round to the whole dollar. Hours are exact.

Step 1The hours at risk

Written Lesson, Sections 1.1.2 and 1.1.3.3

Proposal hours are indirect labor. Our firm pays for them and bills none of them. The hours that cost our firm something are the hours of people who could have been doing billable work instead.

Millbrook RFP 26-014 · Solicitation 26-014, cover sheet
Solicitation26-014, CRA Infrastructure Improvements, Cypress Landing East (CLE) Public Utilities Renewal (TownPUR) Project, RFP (CCNA)
Notification date08 September 2026
Pre-proposal conference15 September 2026, 10:00 A.M.
Written questions close18 September 2026, 5:00 P.M.
Opening date and time29 September 2026, 2:00 P.M.

A non-mandatory pre-proposal conference will be held September 15, 2026 at 10:00 A.M. local time.

Weston & Sampson · time charged to the Millbrook proposal

Five entries were charged to the pursuit. Two of them are not hours of our own technical staff who had billable work available.

Tick the entries that belong in the total. The number fills in below.

How many hours of billable capacity did the pursuit consume?

hours

Two tries. After the second the page shows the worked solution and carries the correct value forward.

Worked solution

Count only our own technical staff who had billable work available.

24 + 10 + 6 = 40 hours

The subconsultant's 12 hours are the subconsultant's cost. Marketing's 30 hours are already indirect labor, so no billable hour is displaced by them.

Step 2The first cost, the salary our firm paid

Written Lesson, Section 1.1.3.1. Method from Module 0, Section 0.2.3.

Our firm paid these people for the time whatever the outcome. That salary moves into overhead, where every project carries a share of it.

Weston & Sampson · the rate build, from Module 0 Section 0.2.3

Technical salary $72,800 a year, across 2,080 working hours.

Unit hourly salary cost = $72,800 ÷ 2,080 = $35.00

Hours at risk, from Step 1This fills in when the step above is checked.

What did our firm pay in salary for those hours?

$

Two tries. After the second the page shows the worked solution and carries the correct value forward.

Worked solution

Hours times the unit hourly salary cost.

40 × $35.00 = $1,400

None of it is billed. It lands in overhead.

Step 3The second cost, the work those hours did not do

Written Lesson, Section 1.1.3.1. Method from Module 0, Sections 0.2.2 and 0.2.3.

The same hours could have been charged to a project. At the target ELM each hour of salary cost is meant to produce $3.30 of Net Revenue.

Weston & Sampson · the target rate, from Module 0 Section 0.2.3

$35.00 unit hourly salary cost × 3.30 target ELM = $115.50, the billing rate at the target ELM.

At breakeven the same hour bills at $35.00 × 2.85 = $99.75.

Hours at risk, from Step 1This fills in when the step above is checked.

How much Net Revenue did our firm not earn?

$

Two tries. After the second the page shows the worked solution and carries the correct value forward.

Worked solution

Hours times the billing rate at the target ELM.

40 × $115.50 = $4,620

The $1,400 of salary sits inside the $4,620, because the billing rate is built to recover salary first. The other $3,220 is the overhead recovery and the profit those hours did not earn. Adding $1,400 and $4,620 to reach $6,020 counts the salary twice.

What the pursuit cost

Hours at risknot yet
Salary paidnot yet
Net Revenue not earnednot yet

Forty hours. $4,620 of Net Revenue our firm did not earn, with $1,400 of salary inside it that moved into overhead.

At the target ELM, $4,620 of Net Revenue would have carried $1,400 of direct labor, $2,590 of overhead, and $630 of project profit.

The takeaway

A pursuit our firm should have declined does not cost the proposal hours. It costs what those hours would have earned.

That is why the Go/No-Go decision comes before the hours are spent, and not after.